Flood restoration works - Minor landslips package no. 17

  • Project typeEssential Public Asset Restoration (EPAR)
  • Project value$1,173,898
  • Project scheduleEarly 2025 to late 2025
  • Completion Date31 December 2025

We are repairing minor landslip damages that occurred on various roads during the 2022 floods.

This includes repairs in the following areas:

  • Goonengerry Road
  • Left Bank Road
  • Main Arm Road
  • The Pocket Road.

This package of works is known as pack 17.

Location and description of works

Location Description of work Status 
Goonengerry Road (between 63 & 70 Goonengerry Road)
  • Regrade the slope surface, also known as batter.
  • Remove landslide debris from the site.
  • Reshape the table drain according to standard Council specifications and make sure the drainage works properly.

Early to late 2025

Left Bank Road (opposite 551 Left Bank Road)
  • Regrade the slope surface, also known as batter.
  • Remove landslide debris from the site.
  • Reshape the table drain according to standard Council specifications and make sure the drainage works properly.
Early to late 2025
Main Arm Road (between Coopers Lane and Settlement Road)
  • Regrade the slope surface, also known as batter.
  • Remove landslide debris from the site.
  • Reshape the table drain according to standard Council specifications and make sure the drainage works properly.
Early to late 2025
Main Arm Road (near 1516 Main Arm Road)
  • Excavate material from the main scarp to make the slope more stable and blend with the natural slope.
  • Reshape the table drain to meet Council standards and ensure proper drainage.
  • Repair or rebuild the damaged road surface. 
Early to late 2025
The Pocket Road (near 66 Pocket Road)

  • Regrade the slope surface, also known as batter.
  • Remove landslide debris from the site.
  • Reshape the table drain according to standard Council specifications and make sure the drainage works properly.
Early to late 2025

Contact details

Jeeva Selina Ali
02 6626 7000