Main Arm Road - Roadwork between Dry Creek Road and Motts Road

  • Project typeFlood infrastructure repair
  • Project scheduleNovember to January 2025
Main Arm flood repair for web.jpg

We're doing road and drainage works on Main Arm Road, between Dry Creek Road and Motts Road, as part of flood repair work and maintenance work.

Works started Monday 25 November and were expected to be completed in December 2024. This has been postponed to early January 2025 because of wet weather.

Works and traffic impacts

  • Works take place between 7.00am and 5.00pm.
  • Please avoid parking vehicles on the road. 
  • There will be local access for vehicles and pedestrians at all times. Traffic control will be in place.
  • There may be some noise, minor dust and delays to your journey while the work takes place.

We apologise for any inconvenience caused and thank you for your patience while we complete this important work. 

Culvert and drainage work has already been completed back in July 2024.

This work will be funded from Council’s maintenance budget, and a portion of this work is funded by NSW Government through disaster recovery arrangements.

Map of work area - Main Arm - November.jpg