Private works at Milton Street Byron Bay
- Completion Date28 February 2025
Construction works within the road reserve are being carried out along Milton Street Byron Bay associated with the redevelopment of 29 Shirley Street.
The works will be delivered in stages commencing 10 October 2024.
View a plan of the staging zones(PDF, 352KB)
Zone 1
Starting 10 October 2024 for 4 weeks.
- Bulk Earthworks
- Stormwater Drainage
- Roadworks.
Zone 2
Starting approximately 10 November 2024 for 4 weeks.
- Bulk Earthworks
- Stormwater Drainage
- Roadworks.
Zone 3
Starting approximately 10 December 2024 for 9 weeks.
- Bulk Earthworks
- Stormwater Drainage
- Roadworks.
The redevelopment of 29 Shirley Street Byron Bay involves:
- Demolition of existing buildings and tree removal.
- Construction of a residential flat building, comprising of 25 three-bedroom dwellings distributed across four separate two and three-storey buildings with basement car parking, associated landscaping and amenities.
You can view the approval on the DA Tracker.