Repairs to flood damaged roads, bridges and causeways
We've assessed over 600 pieces of infrastructure damaged in the February 2022 floods including:
- Roads
- Bridges
- Causeways
- Guardrails.
The cost of repair and reconstruction works is more than $163 million.
The 600 pieces of infrastructure needing repair were bundled into 41 separate funding applications that were submitted to the State and Federal Governments.
We received funding for 200 of these damages.
Projects planned and under construction
We have now packaged these works by location and type. Find out more about each project and construction timeline by selecting a page below.
- Main Arm Valley flood restoration works (including the section of road between between Main Arm Upper School & Motts Road - COMPLETE)
- Left Bank Road works
- The Pocket Road
- Tristran Parade Landslip
- Coopers Lane Culvert
- Sherrys Bridge - COMPLETE
- Mullumbimby Road
- Johnsons Road
- Wanganui Road
- Huonbrook Road Pack
- Upper Wilsons Creek
- Wilsons Creek Road
- Coopers Creek Road
- Area South Landslip works
- Beatties Creek - COMPLETE
- Restoration of the road shoulder on Coopers Shoot Road and Picadilly Hill Road.
- Minor Landslips Pack
- Gravel Roads Pack
- Bridge Guardrail Pack.
Completed priority flood projects
Funding
Project budgets include administrative costs as well as construction costs.
These projects are jointly funded by the Australian and NSW Governments under the Disaster Recovery Funding Arrangements.